Posts

Welcome to the Blog

Ground frame progress: Reassembly

Image
 At the very start of the signalling project, we recognised the need to refurbish the existing ground frames on the running line, and upgrade them to tie in with the signalling 'proper'. The main ground frame will be located close to the Junction box, and is to be called the Junction Ground Frame. The rodding run for this is almost complete. It will eventually be replaced by the new Junction signal box itself...      The ground frame had 4 levers when we started, but had space for 5. This was very fortunate, as we needed 5 levers! Sadly, as we scoured the site to identify signalling components, we could not find another lever. Thanks to our good friend, Keith at the Nene Valley Railway, we obtained a suitable 5th lever. This ground frame controls access to the Turntable Road from the Eden Valley line, as well as the main crossover between the Eden Valley and Tebay lines. The former requires only the Eden Valley train staff to be tied up, but the latter requires both ...

Another Balancing Act...

Image
 ...juggling next?  Having received the new castings for the balance lever pivots, time presented itself to get them drilled and ready for fitting. The four mounting holes had little depressions cast into the backing, to allow easy centering of the drill. Once clamped down onto the radial arm drill, these were a very simple job. The main pivot support, however, was a little more involved. There was no centre marking, so the centre had to be found and marked. Whereas with some of the dismantling work, it had been possible to find the centres of some pins by eye, these required more finesse! Rob offered a very handy tool, which was put to good use. First of all, a blob of paint was daubed in the central area of the casting and allowed to dry: this was so that the scribed lines would show up better. Next, the centre lines were scribed across this paint, and luckily they all met up! Several lines were thrown across, just so that any inaccuracies would be revealed. Rather than use ...

Lintel Time!

Image
After a full day's work today installing six lengths of bullhead rail as ‘lintels’ for the two leadout slots, we finished considerably wiser than when we started! They are quite possibly the heaviest, most awkward and, not to mention, dangerous pieces of kit imaginable. We were very fortunate to have Mike Pattinson, our indefatigable Permanent Way Coordinator, on hand to show us how the job should be done both competently and safely. Many thanks, Mike - a superb job. With this work now complete, we are free to continue bricklaying around the entire perimeter of the building, which will secure the rails firmly in place. The weather is being kind to us at the moment, so hopefully there will be further progress to report soon.

Slowly But Surely!

Image
The brickwork on the Junction Signal Box is gradually rising, in between pauses to position the leadout bench rails and access slots for the signalling wires. In addition, we are making some steel stools to provide intermediate support for the slot support rails. The minutiae seem endless, but progress is slowly being made. Looking at the pointing, you could be forgiven for thinking that some of it is sloppy and untidy. It certainly looks that way, but I hasten to point out that this is efflorescence: a white, powdery salt deposit that forms when water containing dissolved minerals from the cement migrates to the surface of the newly laid brick and evaporates, leaving deposits around the freshly pointed joints. It certainly makes a right mess! Let’s hope this weather holds a while longer so that I have more progress to report soon.

Many Hands...

Image
Over August we have tackled a wide range of jobs, some of which are described herein; others in separate posts. We were very fortunate to have a working visit from friends at the Corris and Ffestiniog Railways. Their presence, support and hard work were greatly appreciated, and saw further leaps in progress! Thank you to Samuel and Joe! Steve will relate the progress with track circuits and location cupboards separately, but work from this session did contribute heavily towards that. The lead out bench was completed, with all the flat wheels for the operational signals bolted down into their positions. This necessitated the use of a stringline to ensure the wire runs did not foul one another as they proceeded towards the next bench. The only remaining job here is to make a few new spindles to suit the assemblies. Next up to be tackled was the cross rod for No.9 FPL, which required digging out more ballast between the sleepers and inserting a couple of rodding rollers to support the cro...

Supporting the Leadout Bench

Image
A high-intensity, all-action day on site saw three members of the team heaving, wrestling, levering, wedging, propping, bolting and finally concreting all ten lengths of supporting rail for the leadout bench into their final resting places. This was quite a big job, as I’m sure you will appreciate. Those lengths of rail will go where they want to go, not where you want to put them, and they really took some persuading. The next job will be to brick them into the walls on which they are now resting, completing an immensely strong and stable base for the installation team to build upon. Very shortly, we will be wrestling with the even longer lengths of rail that will support the brickwork over the leadout slot, but that is another story.

From Little Acorns…

Image
With a shed-load of building materials delivered and stored on site, we have today recommenced work on the junction box. The base of the north-side lead-out slot has been precisely aligned with the adjacent running line to the S&T's requirements. It has been lined with flagstones and will not require any further attention until we have completed a similar construction on the south side of the box. Work on this has now begun, with the rough placement of some of the railway lines that will act as supports for the huge lead-out bench timbers that Tim and his team will fit in due course. We still have a long way to go, but "from little acorns mighty oaks do grow", and with your continued help and support, come hell or high water (and we do get plenty of high water up here!), we absolutely will resurrect this building. So keep watching!