Ground frame progress: Locking

Image
Having assembled and fettled the ground frame, so that each lever worked smoothly and the catch engaged properly, it was time to tackle the locking. Lever 1 was our 'new' lever, and to be used as the release lever, with the Annett's Lock fitted. Nothing can be moved unless the train staff is captive in this lock. This prevents any train movements taking place elsewhere, in conflict to the operation of the ground frame. Pulling Lever 1 releases Lever 2 (or lever 5). Lever 2 is the facing point lock on the Eden Valley line for the Turntable road. Pulling the lever withdraws the bolt from the points, and this action releases Lever 3. Lever 3 operates the points and trap points to allow access to or from the Turntable Road from just outside the Junction box. These are normally set for the running line. Lever 5 is released by Lever 1 only if Lever 2 is not pulled. It controls the facing point lock for the main junction point governing travel to either the Eden Valley line or the...

Ground frame progress: Reassembly

Image
 At the very start of the signalling project, we recognised the need to refurbish the existing ground frames on the running line, and upgrade them to tie in with the signalling 'proper'. The main ground frame will be located close to the Junction box, and is to be called the Junction Ground Frame. The rodding run for this is almost complete. It will eventually be replaced by the new Junction signal box itself...      The ground frame had 4 levers when we started, but had space for 5. This was very fortunate, as we needed 5 levers! Sadly, as we scoured the site to identify signalling components, we could not find another lever. Thanks to our good friend, Keith at the Nene Valley Railway, we obtained a suitable 5th lever. This ground frame controls access to the Turntable Road from the Eden Valley line, as well as the main crossover between the Eden Valley and Tebay lines. The former requires only the Eden Valley train staff to be tied up, but the latter requires both ...

Another Balancing Act...

Image
 ...juggling next?  Having received the new castings for the balance lever pivots, time presented itself to get them drilled and ready for fitting. The four mounting holes had little depressions cast into the backing, to allow easy centering of the drill. Once clamped down onto the radial arm drill, these were a very simple job. The main pivot support, however, was a little more involved. There was no centre marking, so the centre had to be found and marked. Whereas with some of the dismantling work, it had been possible to find the centres of some pins by eye, these required more finesse! Rob offered a very handy tool, which was put to good use. First of all, a blob of paint was daubed in the central area of the casting and allowed to dry: this was so that the scribed lines would show up better. Next, the centre lines were scribed across this paint, and luckily they all met up! Several lines were thrown across, just so that any inaccuracies would be revealed. Rather than use ...

Lintel Time!

Image
After a full day's work today installing six lengths of bullhead rail as ‘lintels’ for the two leadout slots, we finished considerably wiser than when we started! They are quite possibly the heaviest, most awkward and, not to mention, dangerous pieces of kit imaginable. We were very fortunate to have Mike Pattinson, our indefatigable Permanent Way Coordinator, on hand to show us how the job should be done both competently and safely. Many thanks, Mike - a superb job. With this work now complete, we are free to continue bricklaying around the entire perimeter of the building, which will secure the rails firmly in place. The weather is being kind to us at the moment, so hopefully there will be further progress to report soon.