Ground frame progress: Reassembly
At the very start of the signalling project, we recognised the need to refurbish the existing ground frames on the running line, and upgrade them to tie in with the signalling 'proper'. The main ground frame will be located close to the Junction box, and is to be called the Junction Ground Frame. The rodding run for this is almost complete. It will eventually be replaced by the new Junction signal box itself...
The ground frame had 4 levers when we started, but had space for 5. This was very fortunate, as we needed 5 levers! Sadly, as we scoured the site to identify signalling components, we could not find another lever. Thanks to our good friend, Keith at the Nene Valley Railway, we obtained a suitable 5th lever.
PAINT WAS A BAD IDEA!!
Once everything was bolted back together, fettling parts was the primary concern. With having added an extra lever, and shuffled the quadrants about, we needed to make everything fit and work smoothly BEFORE starting on the locking itself. The catch handles had to operate the catches enough to clear the raised slides, and drop in to place at either end of the stroke without slopping around.
Finally, the Annett's Lock was fitted to Lever 1, and the plunger tested.














Comments
Post a Comment