Finally Finishing Fascia!

We were inactive on the signal box all last week due to the appalling weather, but Saturday saw us able to complete the fixing of the expensive sapele fascia boarding that had been dangling all week from a few hastily installed nails. A trial fit of the boarding was deemed necessary because the building is not absolutely square – with the rear wall being thicker at one end than the other and thus all of the rafters on the rear of the building gradually increase in length as they progress from one end of the building to the other. All of these variations need to be accommodated and manipulated in order to produce a neat finish which I think we have done.


There are some inaccessible areas of timber that will need painting before we begin fitting the slates. We hope to get this done by the end of the week and commence slating immediately afterwards.

I will keep you updated stage by stage. 