Almost Ready for the Big Pour
Work on our latest project recommenced today as we began cutting and laying the steel
mats that will further reinforce the concrete cap. Two layers of the mat are required – one at
the base of the trench and another just under the surface of the cap. Liquid concrete will flood
all around and under these binding the whole of the base together into one big solid mass. We
have some finishing touches to apply yet before we concrete and I will report on these with
some explanatory photos in the next post.
If any of you are planning to visit our imminent Easter event for a train ride, you will have
an excellent view of the emergent ‘box as the train rolls by.
Comments
Post a Comment