The Locking Room – Part 3

The latest update from our Civil Engineering Team Leader, Bob Tyson:

Blessed with a glorious day yesterday and a seven strong team on site, great strides were made on our signal box project. A herculean effort by the team saw the best part of 200 concrete blocks unloaded from an adjacent flat wagon and stacked in the confines of the locking room ready for use.

The next few hours saw the locking room walls rise to within inches of the operating room floor level and we also incorporated the lintel over the locking room window opening to give a true flavour of the actual building at last. However, constructing the outer wall from random sandstone will undoubtedly take a little longer, but watch this space!