Happy New Year everyone and so it has turned out so far, with a volte-face in the atrocious weather over the holiday enabling us to make significant progress on the signal box.

It has to be said though that although the weather prevented us from building, we were not idle as stocks of sand, cement, blocks and stone all needed replenishing and transporting to site in preparation for the next assault.


This done, the blockwork forming the internal walls has been raised up to window level on the west wall, with the front wall requiring but a single further course to complete. The east wall which incorporates the locking room doorway is lagging behind somewhat awaiting some realignment of the truculent rear wall, which forms part of said doorway, to enable us to continue. We intend to tackle the problem very shortly and I look forward to reporting a successful outcome (i.e. nothing falling down).

Meanwhile, the stone facing on the west facing wall has grown somewhat in its inexorable and seemingly never ending quest to reach the top.

We intend making the most of this weather and I hope to report further progress very soon!m