If You Go Down (Under The Box) Today...
...you're sure of a big surprise!
The previously prepared girders (which will support the frame) were moved into position, so as to triple check the vertical dimensions. These sit on top of the block pillars that Bob and his team built into the box in the very early days of its construction!
With a little chipping away, dropped mortar was cleared off the top of the plinths, and the two girders lifted into position. These support the frame in the box, with the lever quadrants sitting just above floor level upstairs. Hopefully!
One of the next posts will cover the fastening of the floor to the rails...
In the photos, the two girders are shown temporarily bolted together with studding, to improve stability.