The Locking Room – Part 10
A further report from Bob Tyson following the work that took place on Tuesday last week.
Having placed the lintels in position, we have now brought the walls up to the full height required for installing the first of the two ‘string’ courses which will bring us up to operating floor level thus, in effect, completing the bottom half (the locking room) of the building.
Each stage of the build brings its problems and each problem brings its solution.
I will enjoy documenting these for you as they arise as I know there will be many more to come...